UK Battery Storage Grid Connection Queue Reforms Face Ofgem Scrutiny

2026/09/16 Category:Policy & Future View:50 Comments:0

Great Britain's battery energy storage sector is navigating significant grid connection queue reforms aimed at clearing speculative projects. While the National Energy System Operator has removed hundreds of gigawatts of stalled capacity, regulators note ongoing challenges with missed deadlines and high battery skip rates.

Clearing the Speculative Queue

The National Energy System Operator implemented Target Model Option 4+ reforms to transition the grid connection queue from a first-come-first-served approach to a readiness test. This crucial policy shift successfully removed 153 gigawatts of battery storage projects that were not progressing, ensuring that only deliverable schemes remain in the pipeline.

Before these recent reforms, the connections queue was roughly four times larger than the capacity required to meet the Clean Power 2030 ambitions. The grid operator has now issued offers to more than sixty percent of the projects needed to deliver these national energy targets.

Regulatory Scrutiny and Implementation Challenges

Despite clearing massive capacity, the Office of Gas and Electricity Markets found that the reform process missed deadlines and suffered from poor developer engagement. The regulator highlighted inaccurate connection offers and digitalisation issues with the online portal, acknowledging that the journey was harder than anticipated.

Furthermore, the energy regulator noted that progress on reducing battery skip rates remains significantly slower than initially expected. Industry stakeholders continue to raise concerns regarding transparency and the lack of parity across technology types, indicating that substantial improvements are still required in daily system operations.

Future Capacity and Market Trajectories

The Clean Power 2030 action plan requires between 23 and 27 gigawatts of battery storage capacity to support the clean electricity system. Reaching this ambitious target means the next five years must outbuild the previous eight, driving rapid investment into standalone storage infrastructure across the country.

Installed grid-scale battery capacity reached approximately 7.5 gigawatts by the end of 2025. With the connection queue now successfully rationalised, the strategic focus has shifted towards revenue stacking and long-duration energy storage, ensuring that new agricultural and commercial assets can effectively balance renewable generation.

Key Takeaways

  • The National Energy System Operator removed 153 gigawatts of battery storage projects from the grid connection queue.

  • Ofgem found that the connection reform process missed deadlines and suffered from poor developer engagement.

  • The Clean Power 2030 action plan requires up to 27 gigawatts of battery storage capacity.

  • Installed grid-scale battery capacity in Great Britain reached approximately 7.5 gigawatts by the end of 2025.